ITLEX · Practical guide 01

Ley N.º 9986
SICOP · Costa Rica

Legal remedies in SICOP

Objections, revocations and appeals: identify the appropriate remedy, manage the filing deadline and build an evidence-based challenge in Costa Rican public procurement.

Read the guide

01

The decision determines the remedy.

First identify the decision being challenged and the procurement procedure. Not every disagreement can be challenged, and not every remedy falls within the CGR’s jurisdiction.

Objection

Challenges the solicitation document before bids are submitted. Potential bidders and legally constituted organizations meeting Article 95’s conditions may file.

Appeal

Challenges an award or a decision declaring a major tender deserted or unsuccessful, subject to the applicable participation, standing and substantiation requirements.

Revocation

Seeks review of the final decision by the administration in the cases provided by law and regulation. It is not an appeal to the CGR.

Law No. 9986, Arts. 86, 95, 97 and 99; Regulations, Arts. 241 and 270.

02

Timing is part of the strategy.

These are ordinary filing deadlines, not decision-making deadlines. Check the decision, publication or communication, notification to all parties and applicable calendar before establishing the due date.

Objection · major tender

Decided by the Comptroller General’s Office (CGR).

8 business days

Following publication of the solicitation document.

Ley N.º 9986, art. 95 a)

Objection · minor tender

Decided by the contracting administration.

3 business days

Following communication of the solicitation document.

Ley N.º 9986, art. 95 b)

Objection · reduced tender

Decided by the contracting administration.

2 business days

Following communication of the solicitation document.

Ley N.º 9986, art. 63 n); Reglamento, art. 255

Appeal · major tender

Decided by the CGR; participation and standing are required.

8 business days

Following communication of the final decision.

Ley N.º 9986, art. 97

Revocation · minor tender

Decided by the issuing body; a decision by its head may be requested as provided in Article 99.

5 business days

From the day following communication of the final decision, applying business-day counting rules.

Ley N.º 9986, art. 99

Revocation · reduced tender

Decided by the contracting administration.

2 business days

Following communication of the final decision.

Ley N.º 9986, art. 63 l); Reglamento, art. 270

Counting starts on the business day after all parties have been notified (Law, Art. 86; Regulations, Art. 242), taking account of the trigger for each remedy. This overview does not cover every special regime, amendment to a solicitation or special cases within reduced procedures. Do not automatically apply these deadlines to another tender.

03

Disagreement is not enough.

A challenge must connect verifiable facts, a material legal infringement and appropriate evidence. Grounds must accompany the initial filing; do not rely on completing them later.

  • Identify the infringement

    Specify the clause or part of the decision challenged, the rule or principle infringed and the relief sought.

  • Provide technical evidence

    When challenging a technical requirement, supply supporting studies and evidence. A commercial preference does not establish a legal infringement.

  • Establish standing and a better entitlement

    For challenges to final decisions, assess your eligibility and ability to obtain the award where required. Challenging another bid does not alone establish your entitlement.

  • Check preclusion

    An argument that should have been raised earlier may be precluded. Distinguish an established clause from a subsequent amendment that can still be challenged.

Law No. 9986, Arts. 87, 88 and 90; Regulations, Arts. 245, 246 and 256.

04

The law, applied to the record.

Read decisions in full: facts, the subject of the contract, procedural stage and applicable rules define the scope of each principle.

R-DCP-SICOP-02004-2026 · 3 November 2026

Clarity in monthly service acceptance

In an objection concerning CCSS security services, the CGR partly upheld the claim only to require clear deadlines and conditions for monthly service acceptance. Other alleged infringements concerning payment commencement and deductions were not established. This case-specific correction is not a general prohibition on deductions. Source: full decision, p. 3.

Read decision

R-DCP-SICOP-02001-2026 · 3 November 2026

Evidence and a better entitlement must be established

In an appeal concerning paint for MOPT, the CGR summarily rejected the challenge as manifestly unfounded. The appellant did not provide formal expert or documentary evidence technically refuting the disputed certification. Its potential score of 86.5% also remained below the awardee’s 87.4%. Challenging a competing bid alone did not establish a better entitlement. Source: full decision, pp. 3–4.

Read decision

A previous decision does not guarantee the same outcome in another procedure.

05

A document alone does not complete a filing.

Article 87 requires filing through the unified digital system. The Regulations require the designated electronic form, with attachments providing evidence for the arguments made.

  1. 01
    Review the record

    Gather the tender number, solicitation and amendments, final decision, notifications, bids and relevant evaluations.

  2. 02
    Use the appropriate form

    Set out the arguments in SICOP’s designated remedy fields. An attachment or email is not a substitute for the required form.

  3. 03
    Verify representation and signature

    Confirm the filer’s authority and required signature. Check every attachment for completeness and relevance.

  4. 04
    Retain proof of filing

    Confirm successful submission, retain the receipt and monitor notifications and hearings. Uploading a file does not by itself establish that a remedy has been filed.

Law No. 9986, Art. 87; Regulations, Arts. 243 and 244. All hours of the deadline day are valid for filing; do not wait until the last moment.

06

Sources and editorial scope

  • General Law on Public Procurement No. 9986

    Arts. 63 and 86–99. Statutory text consulted in the supplied consolidated edition updated to October 2026, pp. 122–138.

  • Regulations to Law No. 9986 · Decree No. 43808-H

    Arts. 241–271. Regulatory text consulted in the same edition, pp. 422–451.

  • Reference edition: Sofía Espinoza Salas · EDNASSS / CCSS, 2026

    Ley General de Contratación Pública y su reglamento: concordada y comentada. This original overview summarizes statutory provisions and does not reproduce the author’s commentary.

  • CGR criteria · ITLEX Insights

    Repository for consulting decisions of Costa Rica’s Comptroller General’s Office.

This guide provides preliminary general information only. It is not legal advice, does not guarantee an award or outcome, and does not create an ITLEX-client relationship. Check current rules, the procurement record and deadlines for your specific circumstances. English text is explanatory; the Spanish legal texts govern.

© 2026 ITLEX. Original editorial writing and presentation. The cited public laws and decisions remain public; no exclusive rights over them are claimed.

ITLEX

A remedy calls for an informed decision.

Share the tender, decision and relevant notifications so we can assess the support you need.